OnlyScans · 28 October 2026
Room on top
Dartford, Kent · May 2026 · GPR and ferro scanning
Custodian Data Centres wanted a mezzanine over a suspended, pile-supported slab. We ran GPR grids up to 14 m long across the footprint, every one tied to the engineer’s floor plan. Here the scan sits back on the slab on a tablet. The engineer had the report, a marked-up plan and the full dataset a day before his deadline.
For Custodian Data Centres